Policy:
Comments on Con Edison Draft New York City Reliability Contingency Plan
October 28, 2026
On October 28, 2026, NYSEIA submitted comments in response to Con Edison's Draft NYC Reliability Contingency Plan.
NYSEIA's comments applaud the NYS Public Service Commission for prioritizing clean, non-emitting resources, and voice support for leveraging battery energy storage systems (BESS) as a rapid and cost-effective solution to address New York City’s forecast transmission security reliability needs.
However, NYSEIA also raises significant concerns about Reliability Asset Dispatch Rights (RADR), Con Edison's proposed ratepayer-funded program to meet reliability needs with distribution-connected BESS. NYSEIA's comments highlight faster and more cost-effective strategies to meet NYC's reliability needs by building upon the Value of Distributed Energy Resources (VDER) tariff -- a proven value-based compensation framework that is foundational to New York's multibillion dollar solar and storage marketplace. NYSEIA asserts that the VDER Value Stack could be leveraged and adapted to meet forecast reliability needs while also helping defer costly ratepayer-funded transmission and distribution system expansion, lowering costs for everyone while delivering direct bill savings to low-income customers through the Statewide Solar for All program.
NYSEIA's opposition to Con Edison's RADR proposal is largely contextual. NYSEIA discourages the Commission from authorizing a new program for Con Edison shareholders to earn a guaranteed profit from distribution-connected BESS at the exact same time that Con Edison is working to undermine competitive BESS deployment in its service territory. NYSEIA asserts that Con Edison is intentionally undermining competitive BESS deployment in its service territory by: 1) violating the NYS Standardized Interconnection Requirements, imposing unilateral and arbitrary technical screens that reduce apparent hosting capacity; and 2) aggressively lobbying against modernizing and strengthening the VDER tariff as recommended by the Department of Public Service, which can increase the reliability and deferral value of BESS for ratepayers. Con Edison's regulatory actions are exacerbating reliability needs in NYC by undermining near-term investment in BESS while impacting solar and storage deployment statewide, jeopardizing federally supported clean energy projects and, by extension, imposing additional cost burdens on utility customers.
NYSEIA posits that Con Edison's efforts to undermine BESS deployment under existing proven frameworks while seeking to advance RADR is a simple reflection of misaligned utility profit incentives. NYSEIA's comments include a robust discussion of utility CapEx bias, a review of the Commission's track record of performance-based ratemaketing coming out of the Reforming the Energy Vision (REV) proceeding, and recommendations to address broken utility incentives, which could prevent future bad-faith regulatory engagement by investor-owned utilities in New York.
In summary, NYSEIA urges the Public Service Commission to take near-term actions on pending matters to accelerate distributed BESS deployment, urges the Commission to convene a technical conference to consider proposals that build upon proven compensation frameworks, and we urge the Commission to overhaul utility financial incentives pertaining to distributed energy resource integration so utility regulatory advocacy is brought into alignment with the public interest.
Click "READ MORE" to view NYSEIA's full regulatory comments.